Pope Engineering - Bill Pope, Managing Director |
|
Specialising in the custom design of industrial processing solutions
For the Te Puke blending plant I chose to use Control-It cards for five
reasons
- 1. Flexibility
- 2. Cost
- 3. Robustness
- 4. Expandability
- 5.
Reliability
The chosen system was a Soft PLC (InControl) supplied from InTouch with
an InTouch SCADA.
Because we only had to buy one card at a time to expand I/O, (with no
back plane, remote I/O or comms card) this made moving, expanding or
changing the plant very easy. Because we had true distributed control
we were able to reduce the cost of automation. With the cards close to
the areas that they were controlling we were able to reduce the number
of connectors, terminal blocks and cable duct sizes.
We found the Control-It cards survived in a harsh environment extremely
well and were tolerant of electrical noise(which in the beginning of
the project was an unfortunate fact of life). The cards and control
system controlled a 25kg bag packer, bulk bin packer, bulk bag packer,
milling, blending and powder transport. There were 250 I/O points and
two serial controls.
Pope Engineering Services Ltd
1118 Victoria Rd
Tauwhare RD4
Hamilton New Zealand
Ph +64 27 484 0302 Fax 07 824 0802 |